Project Description

JURONG AROMATICS COMPLEX | JURONG ISLAND | SK E & C

Industry Type
Petro-Chemical Process

Client
The project is a construction of a new plant for Jurong Aromatics Complex. Engineering firm SK Engineering and Construction which was awarded $950m of the estimated $2bn construction commissioned A&B Scaffold Engineering to provide the scaffold requirements. The project had a ground breaking in 2011 and was completed in 2014. The plant has been designed to produce 1.5 million tonnes of aromatics each year, alongside 2.5 million tonnes of fuel a year.

Purpose
Erection of scaffold for elevator construction.

Scaffold Type
Tower, Access tower, Perimeter

JOB NO 135